GWSR Gotherington Embankment Appeal
GWSR urgently needs to raise funds to cover the cost of the emergency works at Gotherington. If you can help us please check out the dedicated web page at the address below.
Click on the link below to find out more about the Appeal |
Thank you.
Richard Johnson
Chairman GWSR plc
Cheltenham Racecourse Station
New Ticket Office Conversion - Work has had to be paused !
The Board recently asked C&M to construct a new on-platform ticket office at CRC. To accommodate this the Retail department have relinquished 1/3rd of the Shop/Waiting Room space at the southern end of the station building. We were asked to do this as a top priority job as soon as the races were over.
We had a team of C&M volunteers willing to work throughout the week starting on 16th to get enough work done to hand the retail space back to the shop team by Friday 20th March.
The new project has to create a new doorway into this area by removing an existing window and installing a new door and frame to match all the others on site.
Waiting Room/Shop area before work started |
To separate the two areas a new stud wall has been built which is clad with plywood on the retail face, and plasterboard on the ticket office side. Retail required the plywood face so that they can securely fix display materials and install security tie-backs for the display shelving.
Deliveries were arranged to arrive at Winchcombe workshop during the races week as we could not get access to CRC station.
Last Wednesday the truck was pre-loaded with all the materials and equipment needed. By then Barrie S our carpenter had pre-installed the new door into the bare frame and installed the door furniture to save us time on site.
Monday 16th - Despite concerns about the Coronavirus the full team began work on site at about 8am. The first job was to cover all floor areas with hardboard to protect the floor surface and then get the new stud wall up to segregate the two areas.
Materials stacked along the platform ready for use |
John, Keith & Paul cutting the timber studs to length |
The Ticket Office side of the new stud wall |
And the Retail side showing the smooth plywood face |
A temporary access had to be maintained through the stud wall to allow access to the rear of the window being removed. Steve L had come to site, modified the electrical circuits and had new power circuits up and running ready for the retail fridges.
By the end of day one the new stud wall carcass was up and clad on the retail side and the inner face of the wall under the window had been removed ready for the work on the door the following day.
Bob cutting out the old concrete blocks under the window |
The finished area ready for removal of the window and brickwork |
Tuesday 17th - Firstly the old window was removed in one piece by very careful use of the diamond disk cutter and our recently acquired multitool. Once the window was out of the way the diamond disk cutter was brought into action. As can be seen in the photos, John is very deft with the use of this machine.
John S on the diamond tipped disk cutter |
and within 15 minutes all the bricks had been removed from the opening.
The removed bricks were taken away for possible future use |
The complete door and frame were installed and accurate measurements taken as to how much to shorten the door so that it just passes over the inner floor. When the building was originally built the platform and inside floor were laid to the same level, however an 80mm screed was then applied to the floor area, and a vinyl floor laid on top. Our new door has to fit over these to open inwards.
The gap left under the door is for the new ramp up to match floor level |
A great deal of care was taken with packing and fixing the frame to the opening. Unfortunately a number of the frame fixings broke during the installation. Luckily all were able to eventually be extracted and replaced with bigger tougher units. I think we had a bad batch of these, and so won't be using them again.
By the end of the day the door was in and locked securely. By now the concerns over Coronavirus had escalated and we had heard that all railway operations were cancelled indefinitely. We had a discussion and the whole team agreed to do one more day to finish off the ticket office side of wall, to point up the door frame and remove all surplus materials back to the C&M workshop at Winchcombe.
The original plan had been to crack on and cut out the new ticket window openings in the south wall of the building, but we needed to get structural lintels from the builders merchants to finish that task and we could not guarantee to finish the work if for any reason they did not have the required stock.
We had not been able to pre-order these as there was ambiguity about the wall construction on that end wall, and so we needed to see what we found when we created the new openings. At this stage the concerns were being voiced about us continuing with the work as we are mostly in the high-risk category for getting the virus due to our age 😕.
Wednesday 18th - The plasterboard was collected from Winchcombe and the wall finished complete with thermal/noise insulation.
Ticket Office side of the new wall ready for a future plaster skim |
Surplus materials, tools and all the debris were loaded onto the truck and returned to Winchcombe.
The remaining team members primed the plywood face of the new wall, primed the new door and pointed up the door frame.
Retail side of wall with first coat of primer applied |
Scaffolding was then erected inside the new ticket office for whenever work resumes cutting out the new window openings. The site was left secure, clean and tidy.
The finished door before painting |
And John giving it its first coat of primer |
It is a shame that we could not get as far as we originally hoped, but we had planned a full week's work, and still believe retail could have had the shop space back by Friday if the Coronavirus had not caused us to stop work. All parties now agree that we stopped at the right point. Let's hope the pause is not too long.
The partially finished waiting room with new power points |
Thanks to all the volunteers who gave up their time for this project. The team were - Bob W, John S, Keith S, Paul C and Steve L (electrician). It was a pleasure to be part of this team.