First a shot in the workshop of Mike painting the frame for a new door made by Barry for the storeroom on P2 at Toddington.
Here is the door painted up.
Again most of the action out on the road was at Cheltenham with a team concreting the holes around the two gate posts.
A start was also made on welding four brackets to each of the posts which will support the large and very heavy fence panels which will run outwards from the gates.
The two pictures above show Mike welding the brackets on to one of the fence posts.
Here is the first fence post installed, complete with 4 brackets (in the background, behind the gate post in the foreground)
Post 1 has shuttering in place and the concrete is being tamped. |
Rob was on tamping duty, and you see him here on post No. 1 and on the right with post No. 2.
looking good! Real level crossing gates required now.