This report covers work done last Saturday and Wednesday. The pictures for this week were taken on Tuesday, when yours truly was passing through early on a grey, grizzely day.
On Wednesday, two of the gang had to do
some remedial work at Toddy, where the wind had lifted the ridge roof
flashing off part of the small waiting room on platform 2. Once done, they
joined in the fun at Winchcombe.
This picture shows all the sleeper type corbelling blocks removed, and a new line of bricks being laid in front, to continue the former slope as part of the extension length. The signal is 'off' but there isn't really a train due - the class 73 was about with the ballast train at Stanton.
Wednesday was spent by the gang
continuing the rebuilding of the old slope section and extending the
concrete blocks towards Cheltenham.
Due to a bit of over enthusiasm
last Saturday we had to redo a short section to get us back on level so
it should be all systems go from here on in.
What also makes this
build difficult is the fact than the wall is on a continuous curve so
it's a case of short sections at a time.
 |
Progress on Tuesday. The blockwork has been extended since then, and it's piled up ready to go. |
One other job that we have
been doing is preparing an area behind the B&S shed which will be used for
storing edging slabs from CRC2 and other building materials.
 |
The sleeper ends that were in use as corbels, as well as some original slabs |
Most of the
work has now been completed, and now that a member has got his telehandler ticket
we can get the slabs in from Cheltenham and get them sorted. These slabs are the natural stone ones not re-used at CRC as too damaged. However, there are good ones among them, and they can also be improved by turning on their backs, and sawing off the rough sides. A number have been taken to Broadway for use in the two gaps (now only one) that remained in the platform. Others will be used by B&S for this Winchcombe platform extension, while more still are pencilled in for Hayles Abbey halt, which will be reinstated as a heritage project next year. Did you know? We even have an authentic little waiting shelter for it.
Here's what it used to look like:
 |
Photograph: G.Daniels - GWR collection |
Further on a heritage theme, we need a number of GWR cast iron gate posts, the ones with the ball on the end like these:
It might be worth having our own cast, like the lamp posts at Broadway, but we need to order several to make commissioning the pattern worth while. Is anyone else interested? Surely there must be some areas on the railway that would be improved by genuine gate posts?
Further to last week's poser picture, here is the answer:
Yes, it was indeed Cheltenham Lansdown, with 7005
Sir Edward Elgar. In fact, Sir Edward took over from another engine that brought the train in, and John Diston took a picture of that as well, in fact it was the first of the two he took.
Here it is:
The reason I didn't show it first is that you can see the running in board under the canopy, and 7005 waiting patiently in the yard behind - too easy ! The incoming engine was 45552
SILVER JUBILEE. The headboard of The Thames, Avon and Severn LCGB Rail Tour has already been taken off.
You're not going to jump on the track, that chap on the left, are you? That tweed jacket may be the uniform of the day, but it gives very limited protection from passing trains.
We have now found a photographer for the B&S activities, so we hope to be able to show you regular photographs of the work as it progresses.